Construction of Sovereign Court started in January 2014.

The development is being built in two phases to ensure public car parking spaces are provided throughout the construction project.

The first phase (January 2014 - spring 2017) will demolish the eastern half of the car park and the vacant West 45 offices. It will deliver 249 homes (51 of which will be affordable) and 5,000 sq ft of commercial space. The first phase of the new public car park opened in May 2016.
 
The demolition works for the western half of the site (which will deliver the second phase of the development) started in May 2016.

A camera is taking photographs of the on-going construction works. You can access the images and a time lapse video on the Lobster Cam webpage :www.lobstervision.tv/sovereigncourt